The City has project and construction updates to share with the community:
Murrieta Road – Near Salt Creek
Work on EMWD’s Murrieta Road Transmission Pipeline Project continues to move south on Murrieta Road with construction now occurring near Lazy Creek Road. Travel through the project area remains available in both directions. Please visit www.emwd.org/MurrietaRoad or click here for project updates.
McCall Boulevard - Encanto Road and Oak Hurst Avenue – Resurfacing Project Resurfacing work originally expected to begin this week has been rescheduled to begin Monday, December 13 (weather permitting) on westbound McCall Boulevard between Encanto Road and Oakhurst Avenue. Construction activity is planned to begin at a later start time of 8:30 a.m. while school is in session to minimize impacts to school traffic in the area. Earlier construction start times will be in effect during the school holiday break from December 21, 2021, through January 6, 2022.
Palomar Road at Matthews Road (Case Road) – Storm Drain Improvements
Storm drain improvements are still under active construction in this area. Matthews Road (Case Road) is expected to be reopened the week of December 19, restoring east and west travel along this section of roadway. Palomar Road will remain closed until further notice while construction continues.
Goetz Road - North of South Canyon Drive – SCE Utility Undergrounding Project
Southern California Edison (SCE) continues to make progress on utility undergrounding work along Goetz Road. This project is expected to continue through the end of the year with the contractor performing work from 7 a.m. to 5 p.m., Monday through Friday. Weekend work is no longer scheduled for the project. While travel lanes are open, periodic lane flagging and minor delays should be expected.
Rockport Ranch - Material Import Haul Route Update
Lennar is continuing material import operations to their Rockport Ranch development site. Routes and time frames for trucks transporting material are as follows while school is in session:
Antelope Road / Garbani Road / Briggs Road - Monday through Friday – 8:30 a.m. to 3:30 p.m.
Holland Road - Monday, Tuesday, Thursday, Friday – 9:30 a.m. to 1:30 p.m.
Scott Road /Leon Road – Intersection Improvements
The intersection of Scott Road and Leon Road will be improved with wider lanes and a traffic signal in the upcoming months. Paving of the intersection is scheduled to begin soon and may impact traffic in the area. This project is a joint effort between the County of Riverside, Perris Union High School District, and the City of Menifee. Additional information will be provided as the project work begins.
For questions on the project/construction updates listed, please contact Don Sharp, Construction Manager, at (951) 723-3726 or at dsharp@cityofmenifee.us.