[ARCHIVED] Menifee Street Project and Construction Updates - Week of February 7, 2022

Menifee_Social_Graphic_Construction_Alert_3

The City has project and construction updates to share with the community: 

Murrieta Road – Near Salt Creek  

Night work is set to begin on Sunday, February 6, on EMWD’s Murrieta Road Transmission Pipeline Project in the area of Murrieta Road and Newport Road. Night work is expected to continue weekly from Sunday through Thursday for approximately five weeks with work occurring between 9 p.m. and 5 a.m. 

Please visit www.emwd.org/MurrietaRoad for additional updates on this project. 

McCall Boulevard – Encanto Road and Oak Hurst Avenue – Resurfacing Project  

Sidewalk improvements have been completed and restriping of the roadways is expected to be completed by Friday, February 4. 

Goetz Road – North of Kabian Park – SCE Utility Undergrounding Project  

SCE continues to perform a second phase of utility line undergrounding work on Goetz Road with lane closures in place north of Kabian Park. Travel will be available both northbound and southbound during the project.     

Rockport Ranch – Material Import Haul Route Update  

Materials import operations for the Rockport Ranch development continue along the following routes:  

    Antelope Road/Garbani Road/Briggs Road - Monday through Friday - 8:30 a.m. to 3:30 p.m.

    Holland Road - Monday, Tuesday, Thursday, Friday - 9:30 a.m. to 1:30 p.m.

Hauling on Holland Road will continue to be eliminated on Wednesdays to ease traffic congestion related to the minimum day school schedules in the area. 

Scott Road/Leon Road – Intersection Improvements 

Paving work expected to start on this project has been slightly delayed and is now anticipated to begin Saturday, February 5.  This work is not expected to impact travel lanes at the intersection. 

Menifee Justice Center (Menifee Town Center) 

Onsite work continues at the Menifee Justice Center site. There are no traffic impacts resulting from the work at this time. 

Menifee Road Improvements – North of Matthews Road 

KB Homes is currently constructing off-site improvements on Menifee Road north of Matthews Road. While there are no full lane closures on Menifee Road, there is considerable traffic control in place due to the heavy construction being performed on the roadway. 

The Public Works Department would like to thank the community for their patience as roadway and other improvements are constructed throughout the city, as well as continuing to drive safely and cautiously in both construction and non-construction areas. 

For questions on the project/construction updates listed, please contact Philp Southard, Public Information and Legislative Affairs Officer, at (951) 746-0654 or at psouthard@cityofmenifee.us. 