[ARCHIVED] Menifee Street Project and Construction Updates - Week of July 25, 2022

Menifee_Social_Graphic_Construction_Alert_3

The City has project and construction updates to share with the community: 

Murrieta Road at Newport Road

At this time, there are no road closures for this project; however, EMWD will periodically place traffic control while working on miscellaneous items. 

Please visit www.emwd.org/MurrietaRoad for additional updates on this project. 

Palomar Road at Matthews Road (Case Road) – Storm Drain Improvements

Palomar Road remains open. 

Goetz Road – North of Kabian Park – Southern California Edison (SCE) Utility Undergrounding Project  

SCE has completed the portions of this project requiring traffic control. Undergrounding that continues   on the shoulder of Goetz Road is not expected to impact traffic flow. 

Murrieta Road and Sun City Boulevard – Traffic Signal Improvements – Capital Improvement Program (CIP) Project

Sun City Boulevard remains closed east and west of Murrieta Road to support the construction of a new traffic signal at the intersection. This project closure is expected to be in place through Monday, July 30. Additional work will continue in this area through the end of August.  

Scott Road between Menifee Road and Briggs Road – Sumac Ridge Utility Work

Intermittent traffic control continues along Scott Road. 

Potomac and Meadows Resurfacing – Pavement Management Program (PMP) Project

Slurry seal operations are expected to begin in late August to complete this pavement rehabilitation project. For  a map of street locations that will be resurfaced through this project, please click here to visit the project page on the City’s website. 

Garbani Road and Menifee Road – Traffic Signal Improvements

Traffic signal improvement work continues to require intermittent traffic control near this intersection. Flagmen are present and assisting with traffic flow as shoulder and drainage improvements continue. 

Newport Road and Murrieta Road – SCE Vault and Conduit Installation

SCE continues night work on Murrieta and Newport Roads to support a new vault conduit installation. Working hours will continue to be between 9 p.m. and 5 a.m. for approximately two weeks with alternating lane closures and traffic control configurations.  

Barnett Road and McLaughlin Road – Road Closure Effective July 5

Barnett Road remains closed between McLaughlin Road and Patricia Lane. This closure is expected to remain in place for the next five weeks while the existing dirt roadway is paved by the developer of a nearby residential project.  

Murrieta Road at Rouse Road – Traffic Signal Improvement Project

Intermittent traffic control will take place as the contractor continues to construct the new traffic signals. 

La Piedra Road at Menifee Road – Traffic Signal Improvement Project  

Intermittent traffic control will take place as the contractor continues to construct the new traffic signals. 

Tradewinds Drive and State Route 74 – Street Improvements

The City of Menifee is constructing street improvements in the Tradewinds Development off State Route 74, which will include sidewalk and pedestrian ramp improvements and full removal and replacement of the street section. Work will continue in this area for approximately the next two months.  

Briggs Road and Matthews Road – Road Closure  

Utility work continues in the area of Matthews and Briggs Roads with road closures expected to remain in place until Thursday, August 4.