News Flash Home
The original item was published from 2/10/2023 10:02:12 AM to 2/18/2023 12:00:01 AM.

News Flash

City of Menifee News & Announcements

Posted on: February 10, 2023

[ARCHIVED] Menifee Street Project and Construction Updates - Week of February 13, 2023

Menifee_Social_Graphic_Construction_Alert_3

*NEW* Holland Road Overpass – City Capital Improvement Project


The City has begun construction work related to the Holland Road Overpass project. Holland Rd. between Hanover Rd. and Antelope Rd. will be closed beginning Tuesday, February 14. This is a hard closure of this section and will remain in place for the duration of the project, which is expected to last 18 months. For additional information and to sign-up for project updates, please visit www.hollandoverpass.com.

*NEW* Menifee Road Improvement Project – City Capital Improvement Project

The City’s capital improvement project on Menifee Rd. between Holland Rd. and Camino Crystal is currently in active construction. Work on the medians is expected to begin the week of February 13. Traffic control will be in place during construction, however travel will be open in all directions. Street improvements continue on Scott Road and Lindenberger Road. Work is expected to continue through the end of September.

*NEW* Cherry Hills Boulevard – Communications Utility Work

Mediacom will be working within the roadway on Cherry Hills Blvd. between Bradley Rd. and Sun City Blvd.  Work is expected to be completed by mid-February.  Traffic control will be in place during the project and delays should be expected.

Murrieta Road at Newport Road

Eastern Municipal Water District’s water transmission line project has been completed. Please visit www.emwd.org/MurrietaRoad for additional updates on this project.

 Garbani Road and Menifee Road – Traffic Signal Improvements


Traffic signal improvement work continues for this project. Temporary traffic control is expected to remain in place as necessary through February 2023.

 

McCall Square Traffic Signal


Work continues on the traffic signal and median at McCall Boulevard and Ranch Road as part of the McCall Square project. The construction schedule for this project has been extended and is now expected to continue through April 2023. Traffic control will remain in place for the duration of the project.


Lazy Creek and Sun City Boulevard Pedestrian Improvement Project


The City has completed the work in the Lazy Creek neighborhood.  Work in the area of Sun City Boulevard is expected to continue through the end of this month. Traffic control will be in place at various locations as necessary.


SoCal Gas Company – Gas Line Installation Project


SoCal Gas Company will continue the installation of new pipeline infrastructure in the vicinity of Evans Rd. and Lazy Creek. Lane closures will remain in place for the next several months to support the project.


Matthews Road Closed at Menifee Road - SoCal Gas Company Work


Matthews Road will be closed at Menifee Road during daytime hours while SoCal Gas Company constructs improvements. Work is expected to continue through mid-March 2023. Traffic control will be in place during active construction.

Facebook Twitter Email