[ARCHIVED] Menifee Street Project and Construction Updates - Week of October 17, 2022

Menifee_Social_Graphic_Construction_Alert_3

The City has project and construction updates to share with the community:

Murrieta Road at Newport Road

Night work will begin this Sunday, October 16 through Wednesday, October 19 at the Murrieta Road and Newport Road intersection. Daytime work will start on Wednesday, October 19 on the trench repair on Murrieta Road and Newport Road and traffic control will remain in place during the project work. 

Murrieta Road and Sun City Boulevard – Traffic Signal Improvements – Capital Improvement Program (CIP) Project

Sun City Boulevard is now open at Murrieta Road. Additional work will continue on the project through mid-November.

Scott Road between Menifee Road and Briggs Road – Sumac Ridge Utility Work

Street improvements continue on Scott Road and Lindenberger Road. Work is expected to continue through the end of October.

Garbani Road and Menifee Road – Traffic Signal Improvements

Traffic signal improvement work continues with intermittent traffic control operations occurring near this intersection. Flagmen remain present to assist with traffic flow as shoulder and drainage improvements continue.

Newport Road and Murrieta Road – SCE Vault and Conduit Installation

SCE work on this project on Murrieta Road, north of Newport Road, continues during daytime hours. Traffic control will be set up and removed daily as needed.

Murrieta Road at Rouse Road – Traffic Signal Improvement Project

Intermittent traffic control will take place as the contractor continues to construct the new traffic signals. The project is expected to continue through mid-November.

La Piedra Road at Menifee Road – Traffic Signal Improvement Project

Intermittent traffic control will take place as the contractor continues to construct the new traffic signals. The project is expected to continue through the end of November.

McCall Square Traffic Signal

Work continues on the traffic signal and median at McCall Boulevard and Ranch Road as part of the McCall Square project. Construction is expected to continue through December.

Banner Park Street Paving

Paving in the area of Lindenberger Road and Domenigoni Parkway has been completed.