The City has project and construction updates to share with the community for the week of May 8, 2023:
I-215 LANE CLOSURE UPDATE - Holland Road Overpass – City Capital Improvement Project
The City is actively performing work related to the Holland Road Overpass project. Holland Road between Hanover Lane and Antelope Road will remain closed for the duration of the project, which is expected to last 17 months. There will also be alternating lane closures on the I-215 Freeway from Newport Road to Scott Road during the week of Monday, May 8. Up to two lanes will be closed and one lane will remain open as work is being completed. Expected dates and times are listed below:
Monday, May 8 - Thursday, May 11
- Southbound I-215: 8 p.m. – 4 a.m.
- Northbound I-215: 9 p.m. – 5 a.m.
Friday, May 12
- Northbound I-215: 9 p.m. – 6 a.m.
- Southbound I-215: 11 p.m. – 6 a.m.
For additional information and to sign up for project updates, please visit www.hollandoverpass.com.
*NEW* – Bradley Road at Holland Road – Storm Drain Construction Work
Storm drain facilities are currently being installed adjacent to Holland Road as part of the Menifee 80 residential housing tract. Intermittent traffic control will be in place during construction, which is expected to continue through the end of May 2023.
*UPDATE* – Menifee Road Improvement Project – City Capital Improvement Project
The developer of Cimarron Ridge continues installing underground improvements in the area of Valley Boulevard between McCall Boulevard and Ridgemoor Street. This portion of Valley Boulevard will be subject to lane closures during this work and traffic delays should be expected in the area through mid-May 2023.
*UPDATE* – SCE Work on Menifee Road – Newport to Holland
Southern California Edison (SCE) began trenching new power lines along Menifee Road, from Newport Road to Holland Road. Work is currently active during daytime and nighttime hours at the intersection of Newport Road and Menifee Road. Traffic control will be in place during project work. Message boards containing contact information for the project will also be placed in the project area. Completion of work in this area is now expected to continue through the end of May 2023.
Read our full list of street projects and construction updates at www.cityofmenifee.us/traffic.