Menifee Street Project and Construction Updates - Week of June 5, 2023
*FREEWAY CLOSURE UPDATE* - Holland Road Overpass – City Capital Improvement Project
The City is actively performing work related to the Holland Road Overpass project. Holland Road between Hanover Lane and Antelope Road will remain closed for the duration of the project, which is expected to last 17 months. There will also be alternating lane closures on the I-215 Freeway from Newport Road to Scott Road during the week of Monday, June 5. Up to two lanes will be closed and one lane will remain open as work is being completed. Expected dates and times are listed below:
Monday, June 5 – Thursday, June 8
- Southbound I-215: 8 p.m. – 4 a.m.
- Northbound I-215: 9 p.m. – 5 a.m.
Friday, June 9
- Southbound I-215: 11 p.m. – 6 a.m.
- Northbound I-215: 9 p.m. – 6 a.m.
For additional information and to sign up for project updates, please visit www.hollandoverpass.com.
*NEW* Normandy Road Lane Closure – La Ladera Road to Berea Road
Southern California Edison (SCE) is currently performing utility potholing on Normandy Road between La Ladera Road and Berea Road. Normandy Road will be reduced to a single travel lane with flaggers present to guide traffic movements through the project area. Work will continue through mid-June. Traffic delays should be expected in the project area.
*NEW* Murrieta Road Improvements – City Capital Improvement Project
The City’s roadway improvement project on Murrieta Road will begin Monday, June 5. Intermittent traffic control will be placed along Murrieta Road from the Salt Creek Chanel to San Quintin Drive to support the construction work. Improvements include road widening, storm drain improvements, pedestrian curb ramps and a center median. The project is anticipated to be completed in mid-September, 2023. Traffic delays should be expected in this area during the project work.
*UPDATE* Newport Road at Murrieta Road – Nighttime Lane Closures
Southern California Edison (SCE) began nighttime work installing underground utility lines at the intersection of Newport Road and Murrieta Road. Night work will be performed from 9 p.m. to 5 a.m. through mid-June 2023. Lanes closures will be in place while this project is active.
*UPDATE* - SCE Work on Menifee Road – Newport to Holland
Southern California Edison (SCE) continues trenching new power lines in the right shoulder along Menifee Road, from Newport Road to Holland Road. Work is currently active during daytime and nighttime hours at the intersection of Newport Road and Menifee Road. Traffic control will be in place during project work. Message boards containing contact information for the project will also be placed in the project area. Completion of work in this area is now expected to continue through the middle of June 2023.
Read our full list of street projects and construction updates at www.cityofmenifee.us/traffic.